Read the findings.
Not just the check marks.

An independent component inspection report helps you decide whether a particular lot meets your acceptance requirements. Read the device identity, tested samples, methods and findings together before authorizing a shipment.

Two reports. Different outcomes.

These supplied White Horse Laboratories examples show why a report must be read as a whole. A passing marking check does not override an unacceptable package-body result.

AD5535BKBCZ · external visual inspection · analysis and sample results excerpt.

Acceptable, with recorded observations.

The AD5535BKBCZ report concludes Acceptable. Its analysis also records minor contamination on one sample. The report lists five samples for visual checks, three for dimensions and one for MPT/resurfacing.

Read the observations as well as the conclusion. The number tested and the checks performed tell your quality team what the result covers.

AD9689BBPZ-2600 · external visual inspection · analysis and sample results excerpt.

A useful report can stop a purchase.

The AD9689BBPZ-2600 report concludes Not Acceptable. It records gross contamination suggesting possible re-lidding and excess adhesive on two samples. All thirteen inspected samples are marked not acceptable for package-body inspection.

Other checks on that page are acceptable. Those check marks do not remove the adverse finding. Clarify the disposition with the supplier and laboratory before accepting the lot.

Read the sample count for each check.

The inspected quantity is specific to the method. It is not automatically the entire lot, and an acceptable visual result is not an electrical test result.

Two supplied White Horse report examples
Report scopeAD5535BKBCZAD9689BBPZ-2600
Lot quantity550
External visual inspection5 samples13 samples
Dimensions / weights3 samples3 samples
MPT / resurfacing result1 sampleNot listed as performed
Overall conclusionAcceptableNot Acceptable

The report says pass. What passed?

Watch how visual checks, device identity, electrical testing and the customer’s application answer different questions.

1 min 16 sec · Inspection photographs illustrate processes. Animated signals explain test scope; they are not measured results or a report for an offered MCU lot.
Read the video transcript

I wouldn't release a motor-control chip lot on the word pass alone. I'd read what was checked, how many samples were involved, and which lot the report covers.

Visual inspection records markings and physical condition. It gives us observations about those samples. It doesn't tell us how the complete motor drive will run.

If a device identity check is agreed, ask which field was read, what value was returned, and what it was compared with. A readable identifier is only one observation.

For electrical work, define the fixture, supply, temperature, signals and acceptance limits. Keep the sample count with the result. Confirm the procedure with the laboratory first.

Actual motor performance usually needs the customer's board, approved program, power stage, motor and load. A component report cannot replace that validation.

Let's agree the checks, sample quantity, acceptance criteria and report-to-lot connection before ordering. We'll confirm which work is feasible with the lab.

Send the full part number, quantity, required arrival date and special inspection or programming requirements. That lets us plan the next step around your purchase.

Discuss the lot and inspection requirements

What your quality team should check.

Use the complete report and its supporting lot documents for the shipment being offered.

Part and lot identity

Match the full manufacturer part number, date code, lot quantity and sample labels to the material in your quotation. Read the photographs alongside the printed fields.

Scope and sampling

Check how many units were inspected for each method. Visual inspection, dimensions, resurfacing tests, X-ray and electrical testing answer different questions. An unperformed check is not a passing result.

Analysis and acceptance

Read the laboratory’s observations, photographs and overall conclusion together. Compare them with your agreed acceptance criteria and ask the laboratory to explain any ambiguous finding.

Shipment release

Resolve adverse findings before agreeing shipment. Keep the accepted report with the relevant lot and delivery records so receiving inspection can check the same material.

Agree the checks before the order.

Tell ICstoq what your incoming quality team requires. We arrange independent inspection for supplied lots and agree the laboratory, sampling and report scope with you.

Choose the right test route.

You can nominate an independent laboratory or your own receiving test centre. Additional electrical or destructive checks need an agreed method, sample quantity and acceptance criteria.